|
Last
Updated: 1/2/2003 |
|
|
PROJECT: Project is to install package water quality treatment Best Management Practice (BMP) system at J01P28 (just downstream of the San Joaquin Toll-Road) along Aliso Creek. Water is to be treated to REC 1 standards for bacterial and the treated water is to be returned to the creek. |
|
|
STATUS: |
|
|
|
|
|
Completion Date |
Item |
|
|
County still awaiting
bond from Clear Creek Systems and finalized agreement with MNWD. |
|
|
County submitted the
disbursement request to the SWRCB for accrued costs. |
|
|
We continue to work with
Clear Creek Systems (CCS) to obtain the surety and are pursuing Counsel and Risk
Management approval of language proposed by surety. Earliest Bond submittal
is December 29, 2002. |
|
12/20/02 |
The plans signed by MNWD |
|
|
The plans were submitted
to MNWD on |
|
|
Laguna Niguel City
Council approved the agreement with Moulton Niguel Water District for the
J03P02 indemnification on |
|
|
We continue to work with CCS to obtain the surety.
Earliest Bond submittal is |
|
|
County has received a cost proposal from Clear Creek Systems, Inc. for revision 1 and revision 2 to the construction drawings and has drafted a contract change order for the change in work. |
|
12/06/02 |
Laguna Niguel City Council approved the agreement
with Moulton Niguel Water District for the J03P02 indemnification subject to
minor revisions. These revisions are being worked on between MNWD and The
City of Laguna Niguel. |
|
|
Side Agreement between the City of |
|
|
Verbal assurance of Clear Creek Systems, Inc. that they would be have sufficient capital to obtain necessary bonds in 3 weeks. Notice to Proceed awaiting contractor bonding. |
|
To be determined |
MNWD discharge permit signing still
outstanding. MNWD permit/agreement language complete. Side agreement
language for J03P02 is complete. Dry Weather Nuisance Flow Diversion
Agreement was approved by |
|
|
MNWD discharge permit
signing still outstanding. MNWD permit/agreement language complete. Side
agreement language for J03P02 is complete. Dry Weather Nuisance Flow
Diversion Agreement is submitted for Approval as to Form by |
|
|
MNWD discharge permit
signing still outstanding. MNWD tentatively scheduled the submittal of
permit/agreement language on |
|
|
Notice to Proceed
awaiting Contractor Bond Submittal. Earliest Bond submittal |
|
|
MNWD discharge permit signing still outstanding. Issues regarding 3rd party indemnification being negotiated. |
|
|
Notice to Proceed awaiting Contractor Bond Submittal. |
|
|
Board approved of construction contract with Clear Creek, Inc for installation of the treatment package plant. |
|
|
Moulton Niguel Water District (MNWD) Board approved sanitary sewer discharge permit for backwash water. MNWD council did not sign. |
|
June, 2002 |
Received the Fish and Game Streambed Alteration Agreement number 5-2002-0121 for stagnant plunge pool removal at downstream end of J01P28 structure. |
|
|
Board finding of adequacy of the RMND, filing of NOD, and approval of the utility agreement with AVCA |
|
|
Planning Commission affirms the adequacy of the RMND for the J01P28 Water Quality Improvement project |
|
|
30 days circulation
period starts |
|
|
AVCA approves in concept
the utility agreement for installation and maintenance of the J01P28 Water Quality
Improvement Project. The signed agreement was returned to County in February
for execution by the Board of Supervisors on |