Last
Updated: 1/2/2003
|
|
|
|
PROJECT: The project is to mitigate
bacteriological contamination and postings at |
|
|
STATUS: |
|
|
|
|
|
Date Complete |
Item |
|
|
State
of the Beach report and data analysis is ongoing. |
|
|
State
of the Beach report and data analysis is ongoing. Draft |
|
12/16/02 |
State
of the Beach report and analysis of data is ongoing. Data Mining report
final edits completed for inclusion in State of the Beach report. |
|
12/13/02 |
Contract
summary form, first quarterly progress report, and first grant disbursement
request sent to SWRCB for next-day delivery. |
|
12/11/02 |
Analysis
of data is ongoing. The draft State of the Beach report will be
completed in early January. The team has found bacteria in sediment
samples with higher concentrations found in finer grained sediments.
This raises questions regarding regrowth and resuspension of bacteria
resident in sediments. |
|
12/13/02 |
Disbursement request, quarterly progress report, and
several deliverables sent to SWRCB for period through |
|
12/5/02 |
First
draft of Ocean Institute BMP monitoring plan completed. Monitoring to
be planned for current rain season. |
|
12/2/02 |
Soils
grain size analysis results received. Team continues analyzing data and
preparing State of the Beach Report. |
|
11/25/02 |
After
reviewing validation results from laboratories that perform Microbial Source
Tracking (MST) studies such as those used in the San Juan Creek Watershed
study, it was concluded that results obtained from these methods would still
be rather uncertain. It was decided to use data collected to date,
which is extensive, to prepare the State of the Beach Report, select BMPs and
identify further studies that would help reduce bacterial contamination at |
|
11/19/02 |
Board
of Supervisors authorizes payment to Ocean Institute for BMP installation. |
|
10/23/02 |
Draft
circulation study report submitted to County. |
|
10/23/02 |
Bacterial
source tracking sampling events completed. |
|
10/1/02 |
State
Water Resources Control Board |
|
9/26/02 |
Two
final bacterial source tracking sampling rounds scheduled for October. |
|
9/26/02 |
Circulation
Study sampling completed. Data analysis ongoing. |
|
9/23/02 |
Circulation
Study Started |
|
9/17/02 |
Bacterial
Source Tracking sampling ongoing. Circulation study scheduled for late
September. Sampling to be complete October/November. |
|
9/11/02 |
Contract
amendment and AIT completed to increase SAIC contract so SAIC can do work
originally scoped for HCA. AIT to go to BOS |
|
9/11/02 |
Draft
circulation study workplan submitted to County by SAIC |
|
9/2/02 |
Sampled
around boats over labor day weekend. Investigation ongoing. |
|
8/28/02 |
Ocean
Institute Construction 99% complete. |
|
8/21/02 |
Initiated
first sampling event for bacteriological source tracking. |
|
8/13/02 |
Minutes to |
|
8/1/02 |
Dana
Point Water Quality Task Force meeting. County presented preliminary
results of Data Mining Study. County to proceed with tidal circulation
and bacterial source tracking study. County shooting for completion of
state of the beach report end of calendar year. |
|
7/22/02 |
Consultant
submitted a draft concept memorandum for tidal circulation study. County
to review and work with consultant to finalize tidal circulation plan over
next two to three weeks. |
|
7/19/02 |
County
submitted review comments on data mining report to consultant – SAIC.
Final report expected in two-three weeks. |
|
7/02/02 |
Data
mining report received by county from consultant – SAIC. Review
comments due to consultant |
|
6/25/02 |
Team
coordination – Draft Data Mining report to be complete |
|
6/14/02 |
Initiated
Tidal circulation workplan. |
|
6/12/02 |
DGPS
field survey of sampling points conducted. |
|
5/29/02 |
Ocean
Institute BMPs Installed. Opening date schedule for August 2002. |
|
5/28/02 |
CEQA
categorical exemption filed with |
|
5/13/02 |
Revised
Clean Beaches Initiative funding application submitted. |
|
5/13/02 |
Monitoring
plan for Ocean Institute BMPs started. |
|
5/2/02 |
Design
of Ocean Institute BMPs finalized. |
|
5/2/02 |
http://www.ocwatersheds.com/watersheds/sanjuan_projects_grants.asp
|
|
4/9/02 |
SWRCB
issued a funding reassurance letter to Ocean Institute for BMPs. |
|
3/20/02 |
Initial
Clean Beaches Initiative funding application submitted. |
|
3/20/02 |
Bacteriological
Source Tracking work planning started |
|
3/12/02 |
Data
Mining Started. |
|
3/12/02 |
|
|
2/20/02 |
SWRCB
Representative, Bruce Locken visits project location. |
|
Spring, 2002 |
Ocean
Institute construction started. Completion scheduled for August 1, 2002 |