|
Last
Updated: 1/2/2003 |
|
|
PROJECT: Project is to install package water quality treatment Best Management Practice (BMP) system at J01P28 (just downstream of the San Joaquin Toll-Road) along Aliso Creek. Water is to be treated to REC 1 standards for bacterial and the treated water is to be returned to the creek. |
|
|
STATUS: |
|
|
|
|
|
Completion Date |
Item |
|
|
County still awaiting
bond from Clear Creek Systems and finalized agreement with MNWD. |
|
|
County submitted the
disbursement request to the SWRCB for accrued costs. |
|
|
We continue to work with
Clear Creek Systems (CCS) to obtain the surety and are pursuing Counsel and Risk
Management approval of language proposed by surety. Earliest Bond submittal
is |
|
|
The plans signed by MNWD |
|
|
The plans were submitted
to MNWD on |
|
|
Laguna Niguel City
Council approved the agreement with Moulton Niguel Water District for the
J03P02 indemnification on |
|
|
We continue to work with CCS to obtain the surety.
Earliest Bond submittal is |
|
|
County has received a cost proposal from Clear Creek Systems, Inc. for revision 1 and revision 2 to the construction drawings and has drafted a contract change order for the change in work. |
|
|
Laguna Niguel City Council approved the agreement
with Moulton Niguel Water District for the J03P02 indemnification subject to
minor revisions. These revisions are being worked on between MNWD and The
City of Laguna Niguel. |
|
|
Side Agreement between the City of |
|
|
Verbal assurance of Clear Creek Systems, Inc. that they would be have sufficient capital to obtain necessary bonds in 3 weeks. Notice to Proceed awaiting contractor bonding. |
|
To be determined |
MNWD discharge permit
signing still outstanding. MNWD permit/agreement language complete.
Side agreement language for J03P02 is complete. Dry Weather Nuisance Flow
Diversion Agreement was approved by |
|
|
MNWD discharge
permit signing still outstanding. MNWD permit/agreement language
complete. Side agreement language for J03P02 is complete. Dry Weather
Nuisance Flow Diversion Agreement is submitted for Approval as to Form by |
|
|
MNWD discharge
permit signing still outstanding. MNWD tentatively scheduled the
submittal of permit/agreement language on |
|
|
Notice to Proceed
awaiting Contractor Bond Submittal. Earliest Bond submittal |
|
|
MNWD discharge permit signing still outstanding. Issues regarding 3rd party indemnification being negotiated. |
|
|
Notice to Proceed awaiting Contractor Bond Submittal. |
|
|
Board approved of construction contract with Clear Creek, Inc for installation of the treatment package plant. |
|
|
Moulton Niguel Water District (MNWD) Board approved sanitary sewer discharge permit for backwash water. MNWD council did not sign. |
|
June, 2002 |
Received the Fish and Game Streambed Alteration Agreement number 5-2002-0121 for stagnant plunge pool removal at downstream end of J01P28 structure. |
|
|
Board finding of adequacy of the RMND, filing of NOD, and approval of the utility agreement with AVCA |
|
|
Planning Commission affirms the adequacy of the RMND for the J01P28 Water Quality Improvement project |
|
|
30 days circulation
period starts |
|
|
AVCA approves in concept
the utility agreement for installation and maintenance of the J01P28 Water Quality
Improvement Project. The signed agreement was returned to County in February
for execution by the Board of Supervisors on |
|
|
|
|
PROJECT: The project is to mitigate
bacteriological contamination and postings at |
|
|
STATUS: |
|
|
|
|
|
Date Complete |
Item |
|
|
State
of the Beach report and data analysis is ongoing. |
|
|
State
of the Beach report and data analysis is ongoing. |
|
|
State
of the Beach report and analysis of data is ongoing. Data Mining report
final edits completed for inclusion in State of the Beach report. |
|
|
Contract
summary form, first quarterly progress report, and first grant disbursement
request sent to SWRCB for next-day delivery. |
|
|
Analysis
of data is ongoing. The draft State of the Beach report will be
completed in early January. The team has found bacteria in sediment
samples with higher concentrations found in finer grained sediments.
This raises questions regarding regrowth and resuspension of bacteria
resident in sediments. |
|
|
Disbursement request, quarterly progress report, and
several deliverables sent to SWRCB for period through |
|
|
First
draft of Ocean Institute BMP monitoring plan completed. Monitoring to
be planned for current rain season. |
|
|
Soils
grain size analysis results received. Team continues analyzing data and
preparing State of the Beach Report. |
|
|
After
reviewing validation results from laboratories that perform Microbial Source
Tracking (MST) studies such as those used in the San Juan Creek Watershed
study, it was concluded that results obtained from these methods would still
be rather uncertain. It was decided to use data collected to date,
which is extensive, to prepare the State of the Beach Report, select BMPs and
identify further studies that would help reduce bacterial contamination at |
|
|
Board
of Supervisors authorizes payment to Ocean Institute for BMP installation. |
|
|
Draft
circulation study report submitted to County. |
|
|
Bacterial
source tracking sampling events completed. |
|
|
State
Water Resources Control Board |
|
|
Two
final bacterial source tracking sampling rounds scheduled for October. |
|
|
Circulation
Study sampling completed. Data analysis ongoing. |
|
|
Circulation
Study Started |
|
|
Bacterial
Source Tracking sampling ongoing. Circulation study scheduled for late
September. Sampling to be complete October/November. |
|
|
Contract
amendment and AIT completed to increase SAIC contract so SAIC can do work
originally scoped for HCA. AIT to go to BOS |
|
|
Draft
circulation study workplan submitted to County by SAIC |
|
|
Sampled
around boats over labor day weekend. Investigation ongoing. |
|
|
Ocean
Institute Construction 99% complete. |
|
|
Initiated
first sampling event for bacteriological source tracking. |
|
|
Minutes to |
|
|
Dana
Point Water Quality Task Force meeting. County presented preliminary
results of Data Mining Study. County to proceed with tidal circulation
and bacterial source tracking study. County shooting for completion of
state of the beach report end of calendar year. |
|
|
Consultant
submitted a draft concept memorandum for tidal circulation study. County
to review and work with consultant to finalize tidal circulation plan over
next two to three weeks. |
|
|
County
submitted review comments on data mining report to consultant – SAIC.
Final report expected in two-three weeks. |
|
|
Data
mining report received by county from consultant – SAIC. Review
comments due to consultant |
|
|
Team
coordination – Draft Data Mining report to be complete |
|
|
Initiated
Tidal circulation workplan. |
|
|
DGPS
field survey of sampling points conducted. |
|
|
Ocean
Institute BMPs Installed. Opening date schedule for August 2002. |
|
|
CEQA
categorical exemption filed with |
|
|
Revised
Clean Beaches Initiative funding application submitted. |
|
|
Monitoring
plan for Ocean Institute BMPs started. |
|
|
Design
of Ocean Institute BMPs finalized. |
|
|
http://www.ocwatersheds.com/watersheds/sanjuan_projects_grants.asp
|
|
|
SWRCB
issued a funding reassurance letter to Ocean Institute for BMPs. |
|
|
Initial
Clean Beaches Initiative funding application submitted. |
|
|
Bacteriological
Source Tracking work planning started |
|
|
Data
Mining Started. |
|
|
|
|
|
SWRCB
Representative, Bruce Locken visits project location. |
|
Spring, 2002 |
Ocean
Institute construction started. Completion scheduled for |
|
|
|
|
PROJECT: The purpose of the
project is to reduce bacterial loading and ponding at |
|
|
STATUS: |
|
|
|
|
|
Date Complete |
Item |
|
|
|
|
|
|
|
|
E-mail from |
|
|
E-mail from RWQCB. Additional information requested to process 401 certification. RWQCB requests that some mitigation be
proposed to mitigate the impacts of the project. RWQCB in a telephone conversation states
that such mitigation can potentially be trash pick-up, autumn removal of
tidal barrier and shaping of sand, and practice of noting the presence of
sensitive species prior to maintenance activities. RWQCB also states that some educational
signage could potentially be used as mitigation. |
|
|
Biological survey scoping begun. This is needed as part of the coastal
development permit process with the California Coastal Commission. This will assess what plants and animals
use the Scour Pond and project area as habitat, and what mitigation measures
are needed, if any. This is anticipated
to be completed in January 2003. |
|
|
Wave run-up study started. This is needed as part of the coastal
development permit process with the California Coastal Commission. This will evaluate the impacts of wave
action on any of the project components, and what mitigation measures are
needed to protect project components.
To be completed by end of January 2003. |
|
|
USEPA publishes Finding of No
Significant Difference (FONSI) and environmental assessment for public
review. Public review period ends http://www.haimann.com/poche/Poche_Beach_Public_Notice.pdf
http://www.haimann.com/poche/Poche_Beach_FONSI.pdf
http://www.haimann.com/poche/poche_beach_ea.pdf
|
|
|
City of |
|
|
City of |
|
|
County meets with |
|
|
County meets with Dan Carlson and
Dave Cortens who, on behalf of the |
|
|
Board of Supervisors approves CEQA
Notice of Determination of Mitigated Negative Declaration. Board of Supervisors approves agreement
with City of |
|
|
Army Corps of Engineers (ACOE) is
finalizing permit conditions for the Section 10 and 404 permit. Public notice of the permit is expected to
be sent shortly. Primary permit condition
to finalize is the condition regarding biological monitoring during scour
pond maintenance activities. Current
proposed permit condition is for the County park ranger responsible for the
beach to prepare a preliminary report prior to maintenance activities
regarding whether or not any listed species have been observed in the
vicinity of the work. If so, then a
biological monitor would be required during maintenance activities. If not, then maintenance activities can
take place without a biological monitor. |
|
|
Responses to comments completed and
sent to commenters. Commenters
included City of Dana Point, |
|
|
USEPA is ready to send public notice
of the Finding Of No Significant Impact (FONSI). They are awaiting submittal of grant
application from City of |
|
|
Army Corps of Engineers completes
draft permit for public review. |
|
|
|
|
|
CEQA public comment period closed. |
|
|
California Coastal Commission assigns
staff member Karl Schwing to process permit and review CEQA. |
|
|
Tetra Tech completes 90 percent
design. |
|
|
California Coastal Commission states
tentatively they will have jurisdiction over the coastal development permit for
the project. |
|
|
CEQA Public comment period re-opened
till |
|
|
CEQA Public comment period
closed. Comments received from South
Coast Water District, City of Dana Point, and Caltrans. |
|
|
Public Meeting held at Shorecliff’s
Poche Beach Club House. |
|
|
CEQA Initial Study Mitigated Negative
Declaration (IS/MND) Published. Public
comment period ends http://www.ocwatershed.com/watersheds/pdfs/ndsupinfopoche_04.pdf. |
|
|
Public meeting to be rescheduled for
late October. |
|
|
CEQA Initial Study/Mitigated Negative
Declaration to be sent for public comment |
|
|
Public meeting on hold. Tentative date September 30 |
|
|
County review of 60% design drawings
complete. Comments sent to A/E. |
|
|
Public Meeting Scheduled for |
|
|
County received draft 60% design
drawings from A/E. |
|
|
Project Schedule Posted on web site: http://www.ocwatershed.com/watersheds/pdfs/Poche_Beach_Project_Implementation_Schedule.pdf |
|
|
|
|
|
|
|
|
SCRRA submits questions to |
|
|
13225 directive initial report submitted not San Diego RWQCB. |
|
|
San Diego RWQCB grants extension of
13225 directive initial report to |
|
|
County, City of Dana Point, City of |
|
|
Meeting with railroad scheduled for |
|
|
Meeting with City of |
|
|
San Diego Regional Water Quality Control
Board (SDRWQCB) issued a directive to City of |
|
|
Draft NEPA EA is complete and ready
to be taken over by City of |
|
|
No comments on draft CEQA documents
from resource agencies. CEQA is
waiting for siting decision prior to its completion and submittal to other
stakeholders and County planning department for review and processing. |
|
|
Meeting with Southern California
Regional Rail Authority at site to evaluate location determine license
agreement conditions. Design has been
started. The SCRRA was unconvinced that
the railroad easement was the optimal location for the treatment plant. County proceeding with a cost/benefit
analysis of various treatment plant sites.
Analysis to be complete July 19.
Further discussions with the railroad will ensue. |
|
|
Draft proposed project plan and
initial study (CEQA) presented in a meeting with the San Diego Regional Water
Quality Control board, California State Water Resources Control Board,
California Department of Fish and Game, South Orange County Water Association,
U.S. Army Corps of Engineers, U.S. Fish and Wildlife Service, City of Dana
Point, and City of |
|
|
Draft proposed project plan and
initial study (CEQA) presented in a meeting with the Orange County
Transportation Authority, Southern California Regional Rail Authority, City
of Dana Point, and City of |
|
|
Clean Beaches Initiative funding application
submitted. |
|
|
County staff met with stakeholders,
Shorecliff HOA, on
|
|
|
Board of
Supervisors approves A/E agreement with Tetra Tech |
|
|
Second planning
meeting held with City of SWRCB Rep,
Bruce Locken visited project site. |
|
|
|
|
|
Kick-off
planning meeting held with City of |